Newly Constructed Çöpler Sulfide Plant Processing Sulfide Ore
Sulfide Plant Construction Complete Under Budget

Çöpler Sulfied Plant November 2018
The Çöpler Gold Mine is operated by Alacer Gold and is an open-pit mine that is producing gold from oxide ore via a heap leach operation and also from sulfide ore via a pressure oxidation circuit. In May 2016 construction commenced on the Çöpler Sulfide Expansion Project and construction of the Sulfide Plant was completed ~11% under budget. The Sulfide Plant is operating and producing gold and provides the next stage of growth for Alacer.
Çöpler Sulfide Expansion Project (1)
Plant Started
Third quarter 2018
Pre-Production Capital
~US$660 million (was US$744 million)
Estimated Mine Life
20 years
Remaining Life-of-Mine Production

~3.5 million ounces

Life-of Mine All-in Sustaining Costs
$645 per ounce

(1) On 100% basis